General transmission line installation grfx.png

UPDATE: Due to unfavorable weather conditions, work planned for Friday, Feb. 10 (Martin Rd.) has been postponed to Monday, Feb. 13. Timeline changes are reflected below and subject to change due to weather conditions. Transmission line installation on power structures along SR 400, 306, 369 and Martin ... Read more...

400 NB at 306 9.17.22 closure.jpg

To accommodate the construction of the new interchange at SR 369 and 400, the right traffic lane on SR 400 northbound from exit 17 (Keith Bridge Rd./SR 306) to Martin Rd. will be closed between 9 a.m. and 4 p.m. for approximately one week, ... Read more...

WEB-OTM-Ep4.jpg

On this episode of On the Move, Capital Projects Director John Jefferson provides the latest updates and information on the progress of the interchange at McGinnis Ferry Rd. SR 400, as well as the widening of SR 369. On the Move is a video series ... Read more...

MicrosoftTeams-image (1).png

SR 400 northbound will have a lane closure between SR 306 and 369 to allow for a clearing operation between 7 a.m. and 3 p.m. on Thursday, Jan. 21, and Friday, Jan. 22.The closure is weather dependent so there may be some fluctuation. Updates ... Read more...

MicrosoftTeams-image (1).png

SR 400 will have scheduled daytime lane closures and traffic paces at Pilgrim Mill Road for median construction Monday, Nov. 23, through Tuesday, Nov. 24.Below is the schedule of planned traffic impacts:Monday, Nov. 23 (7 a.m. to 3 p.m.)            ... Read more...

MicrosoftTeams-image (1).png

ForsythCounty and state officials gathered on Tuesday, Nov. 17, to officially breakground on the widening of SR 369 as well as the creation of a grade-separated,partial cloverleaf interchange coming to the intersection of SR 400 and SR 369.  Photos from the event can be found ... Read more...

MicrosoftTeams-image (1).png

SR 400 will have scheduled daytime lane closures and trafficpaces at Pilgrim Mill Road for median construction Monday, Nov. 16, through Wednesday,Nov. 18.Below is the schedule of planned traffic impacts:Monday, Nov. 16 (7 a.m. to 3 p.m.)                 ... Read more...

MicrosoftTeams-image (1).png

SR 400 will have scheduled daytime lane closures and traffic paces at Pilgrim Mill Road for median construction Monday, Nov. 9 through Thursday, Nov. 12.Below is the schedule of planned traffic impacts:Monday, Nov. 9 (7 a.m. to 3 p.m.)            ... Read more...

MicrosoftTeams-image (1).png

SR 400 will have a scheduled daytime lane closure and traffic paces at Pilgrim Mill Road for median construction Wednesday, Nov. 4.Below is the schedule of planned traffic impacts:Wednesday, Nov. 4 (7 a.m. to 3 p.m.)                  ... Read more...

MicrosoftTeams-image (1).png

UPDATE: SR 400 scheduled daytime lane closures and trafficpaces at Pilgrim Mill Road for median construction have been moved from Wednesday, Oct. 28 to Friday, October 30 due to weather.Below is the schedule of planned traffic impacts:Friday, Oct. 30 (7 a.m. to 3 p.m.)•             ... Read more...