Untitled DocumentBuilding Permit Fee| Impact Fees | | Residential Impact Fee calculated by heated area. | | Residential Impact Fee | $0.515 per sq. ft | | Non-Residential Impact Fee claculated by floor area. | | Non-Residential Impact Fee (for retail/commercial) | $0.216 per sq. ft. | | Non-Residential Impact Fee (for office/business) | $0.086 per sq. ft. | | Non-Residential Impact Fee (for industrial) | $0.052 per sq. ft. |
| Building Permits | | Determining Valuation - Non Commercial | | Heated square feet multiplied by $40 = Heated Valuation | | Unheated square feet multiplied by $10 = Unheated Valuation | | (unheated consists of garage, carport, porch, deck, patio, and unfinished basement) | | The sum of Heated Valuation and Unheated Valuation will determine your Total Valuation |
| Non Commercial | | Total Valuation | Fee | | $1,000 and less | Minimum charge $15 | | $1,001 to $50,000 | $15 for the first $1,000 plus $5 for each additional thousand or fraction thereof | | $50,001 to $100,000 | $260 for the first $50,000 plus $4 for each additional thousand or fraction thereof | | $100,001 to $500,000 | $460 for the first $100,000 plus $3 for each additional thousand or fraction thereof | | $500,001 and up | 1,660 for the first $500,000 plus $2 for each additional thousand or fraction thereof |
| In addition to building fee above, Residential HVAC, Plumbing & Electrical Permits | Charge for Each trade (based on heated square feet) |
| 0-1,000 sq. ft. | $30 | | 1k-2k sq. ft. | $40 | | 2k-3k sq. ft. | $50 | | 3k sq. ft. + | $60 |
| Commercial Plan Review - these fees must be paid when plans are submittal | | 5,000 square feet of less | $100.00 | | over 5,000 square feet | $0.025 per square foot. | | Commercial Building Permits | | Enclosed Area | $0.12 per square foot | | Open Area | $0.06 per square foot | | In addition to building permit above HVAC, Plumbing & Electrical permits must be permitted seperate from the building permit. | HVAC Permit | | Plumbing Permit | | Electrical Permit |
| Other Building Permit Fees | | Building Permit Renewal (At least one inspection must have been approved prior to renewal of a permit. Renewals must be made by application within 90 days of the expiration date, and will be limited to one renewal per permit.) | $100 | | Building Re-Permit (Permit has been expired for more than 90 days) | Full Building Permit Fee | | Mobile Home Permits (HUD) | $75 | | Mobile Home Permits (non-HUD) | $100 | | Duplicate Copy of Certificate of Occupancy | $0.25 | | Tenant Change Occupancy | $15 | | Co-locate (Antenna on Cell Towers) | $200 | | Temporary Construction Trailer | $75 |
|
|
|